Moraga plans $16 million modernization phase at Camino Pablo and Los Perales

Facilities
Excerpt from Regular Governing Board Meeting  with Closed Session - Oct 13 2026 for Moraga plans $16 million modernization phase at…
Official source excerpt: Regular Governing Board Meeting with Closed Session - Oct 13 2026; editorial caption by Our School Board · source-evidence

What happened

Phase 2 Measure D modernizations at Camino Pablo and Los Perales remain a district priority, with construction targeted to start in June 2027. The planning budget is $8 million per campus—$6 million in estimated construction costs and $2 million in soft costs—with design completion targeted for October 2026 and state review submission for late November.

Why it matters to families

This outlines a substantial planned investment and timeline for two elementary campuses, though the presentation is a planning update rather than final approval of construction contracts or detailed project scope.

The evidence

At the October 13, 2026 meeting, the Measure D update said Phase 2 modernizations at Camino Pablo and Los Perales remain prioritized over secondary scope items, with a budget of $8 million per site ($6 million estimated GMP and $2 million soft costs). Design completion was scheduled for October 2026, DSA submission for late November 2026, and a June 2027 construction start. The same update said administration was exploring alternative funding for technology upgrades.

The source

Regular Governing Board Meeting with Closed Session - Oct 13 2026

Share this story

Help your community stay informed about the decisions that affect your schools.

Get alerts like this for Moraga School District

We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from, the moment it's public.

Get personalized alerts