Board approves a $2.9 million district office and secure entry project

What happened
On January 19, 2026 the board accepted a $2,897,510.06 bid from Hoeft Builders to build new district and high school offices with a new secure main entrance, by a vote of 5 to 2. The July 2026 update said the project was 23.6% complete and slowed by unforeseen site conditions.
Why it matters to families
The project changes how visitors enter the high school and what the district spends on buildings.
The evidence
Approved minutes record the motion and vote; the monthly CESA 10 update gives the budget and progress.
The source
January 19, 2026 approved minutesSee the full record for Stanley-Boyd Area School District.